95 Lane Closure Content – Week of April 15

April 15, 2019

The express version

  • Weather permitting, there are upcoming closures this week on the I-95 regular lanes in Prince William & Stafford County
  • Look out for detours and drive safely
  • There will be work zones set up in Stafford County starting Monday and ending Friday

Closure this week on I-95 northbound and southbound

Overnight shoulder closures on I-95 northbound and I-95 southbound at various locations between Exit 148 (Quantico) in Prince William County and Exit 136 (Centreport Parkway) in Stafford County. Weather permitting, closures will take place on the following dates and times:

  • Monday, April 15: 9 p.m. to 5 a.m.
  • Tuesday, April 16: 9 p.m. to 5 a.m.
  • Wednesday, April 17: 9 p.m. to 5 a.m.
  • Thursday, April 18: 9 p.m. to 5 a.m.

Closure this week on I-95 northbound

Expect a single lane closure on I-95 northbound near Exit 148 (Quantico) in Prince William County.  Weather permitting, closures will take place on the following dates and times:

  • Monday, April 15:  9 p.m. to 4:30 a.m. 
  • Tuesday, April 16: 9 p.m. to 4:30 a.m.
  • Wednesday, April 17: 9 p.m. to 4:30 a.m. 
  • Thursday, April 18: 9 p.m. to 4:30 a.m.

Closure this week on I-95 southbound

Expect a single alternating lane closure on I-95 southbound near Exit 148 (Quantico) in Prince William County. Weather permitting, closures will take place on the following dates and times:

  • Monday, April 15:  9 p.m. to 10 a.m. 
  • Tuesday, April 16:  9 p.m. to 10 a.m.
  • Wednesday, April 17: 9 p.m. to 10 a.m. 
  • Thursday, April 18: 9 p.m. to 6 a.m.

Stafford County Work Zones

Expect alternating, one-way traffic on Route 628 (American Legion Road) at the bridge over I-95, which is between Bower’s Lane and Ellison Court. A flagging crew will direct drivers through the work zone.

  • Monday, April 15: 9 p.m. to 5 a.m.
  • Tuesday, April 16: 9 p.m. to 5 a.m.
  • Wednesday, April 17: 9 p.m. to 5 a.m.
  • Thursday, April 18: 9 p.m. to 5 a.m.
  • Friday, April 19: 9 p.m. to 5 a.m.

Expect alternating, one-way traffic on Route 630 (Courthouse Road) between Route 1 (Jefferson Davis Highway) and Austin Ridge Drive for utility marking. A flagging crew will direct drivers through the work. 

  • Monday, April 15: 9 a.m. to 3:30 p.m. 
  • Tuesday, April 16: 9 a.m. to  3:30 p.m. 
  • Wednesday, April 17: 9 a.m. to 3:30 p.m. 
  • Thursday, April 18: 9 a.m. to 3:30 p.m. 

More info

Drivers are advised to travel safely and pay attention to on-road signage if traveling in this area during these closures. Visit expresslanes.com/projects/fredericksburg-extension to view additional lane closure information and to sign up for e-newsletters and traffic alerts.