495 Express Lanes repavement week of July 27

July 27, 2020

Expect full closure of the SB 495 Express Lanes this week

The SB 495 Express Lanes from around Gallows Rd. to the Springfield Interchange will be closed. The Lee Highway, I-66 EB and I-66 WB ramps to the SB 495 Express Lanes will also be closed. Traffic will be detoured to Gallows Rd, please follow posted detour signs. Weather permitting, the closure will take place at the following time:

  • Monday, July 27: 9 p.m.-6 a.m.

The SB 495 Express Lanes will be closed from around I-66 to the Springfield Interchange. The Lee Highway, I-66 EB and I-66 WB ramps to the SB 495 Express Lanes will also be closed. Traffic will be detoured to I-66 WB, please follow posted detour signs. Weather permitting, the closure will take place at the following time:

  • Tuesday, July 28: 9 p.m.-6 a.m.
  • Wednesday, July 29: 9 p.m.-6 a.m.

There will also be closures in the regular lanes on I-495

The left lane of the SB I-495 regular lanes from around Gallows Rd. to the Springfield Interchange will be closed due to repavement on the 495 Express Lanes. Weather permitting, the closure will take place at the following time:

  • Monday, July 27: 9 p.m.-6 a.m

The left lane of the SB I-495 regular lanes from around I-66 to the Springfield Interchange will be closed due to repavement on the 495 Express Lanes. Weather permitting, the closure will take place at the following time:

  • Tuesday, July 28: 9 p.m.-6 a.m.
  • Wednesday, July 29: 9 p.m.-6 a.m.

Closures continue into the weekend

There will be a closure from the start of the NB 495 Express Lanes until Route 29/Lee Highway. Braddock Rd. and Gallows Rd. ramps will also be closed. The left lane of the SB I-495 regular lanes will also be closed from the start of the NB 495 Express Lanes until Route 29/Lee Highway. Weather permitting, the closures will take place the at the following times:

  • Saturday, August 1-Sunday, August 2: 9 p.m.-9 a.m.