395 Lane Closure Content – Week of September 16

September 15, 2019

The express version

  • Weather permitting, there are upcoming lane and ramp closures on the I-395 HOV and regular lanes
  • Look out for detours and drive safely

Be prepared for overnight and daytime HOV lane closures

Roadwork for the I-395 HOV lanes requires an overnight closure of the HOV lanes from near Edsall Rd. to the 14th St. Bridge. Weather permitting, the closure will take place during the following times:

  • Monday, September 16: 8 p.m. to 4:30 a.m.
  • Tuesday, September 17: 8 p.m. to 4:30 a.m.
  • Wednesday, September 18: 8 p.m. to 4:30 a.m.
  • Thursday, September 19: 8 p.m. to 4:30 a.m.

Roadwork along the I-395 HOV lanes may require daytime closures to accommodate project activities. Weather permitting, closures would potentially take place during the following times:

  • Monday, September 16: 9:30 a.m. to 2 p.m.
  • Tuesday, September 17: 9:30 a.m. to 2 p.m.
  • Wednesday, September 18: 9:30 a.m. to 2 p.m.
  • Thursday, September 19: 9:30 a.m. to 2 p.m.

Due to scheduled bridge rehabilitation work in the areas of Sanger Avenue and Braddock Road, HOV closures are will depend based on traffic for the weekend starting on Friday, September 20, at 11:00 p.m through Monday, September 23, at 4:00 a.m.

Also be on the lookout for closures on the regular lanes

Daytime closures in the I-395 south right regular lanes will occur during the following times: 

  • Monday, September 16: 9 a.m. to 2:30 p.m.
  • Tuesday, September 17: 9 a.m. to 2:30 p.m.
  • Wednesday, September 18: 9 a.m. to 2:30 p.m.
  • Thursday, September 19: 9 a.m. to 2:30 p.m.

Daytime closures in the I-395 north left regular lanes will occur during the following times: 

  • Monday, September 16: 10 a.m. to 3 p.m.
  • Tuesday, September 17: 10 a.m. to 3 p.m.
  • Wednesday, September 18: 10 a.m. to 3 p.m.
  • Thursday, September 19: 10 a.m. to 3 p.m.

Roadwork along I-395 south will require an overnight, single-lane closure on the right regular lane. Weather permitting, closures may take place on the following nights:

  • Monday, September 16: 12 a.m  to 4:30 a.m.
  • Tuesday, September 17: 12 a.m  to 4:30 a.m.
  • Wednesday, September 18: 12 a.m  to 4:30 a.m.
  • Thursday, September 19: 12 a.m  to 4:30 a.m.

Roadwork along I-395 south will require an overnight, two-lane closure on the left regular lanes. Weather permitting, closures may take place on the following nights:

  • Monday, September 16: 12 a.m  to 4:30 a.m.
  • Tuesday, September 17: 12 a.m  to 4:30 a.m.
  • Wednesday, September 18: 12 a.m  to 4:30 a.m.
  • Thursday, September 19: 12 a.m  to 4:30 a.m.

There will also be multiple ramp closures this week     

Roadwork along I-395 North will require overnight total closures of the I-395 NB exit ramps on to Route 27/Washington Blvd (Exit 8A) and Route 27 North/110 South (Exit 8B). A detour will be in place. Weather permitting the closure will take place during the following times:

  • Monday, September 16: 12 a.m  to 4:30 a.m.
  • Tuesday, September 17: 12 a.m  to 4:30 a.m.
  • Wednesday, September 18: 12 a.m  to 4:30 a.m.
  • Thursday, September 19: 12 a.m  to 4:30 a.m.
  • Friday, September 20: 12 a.m  to 4:30 a.m.
  • Saturday, September 21: 12 a.m  to 4:30 a.m.

Roadwork on I-395 SB will require overnight total closures of the exit ramp on to King Street (Exit 5). A detour will be in place. Weather permitting the closure will take place during the following times:

  • Monday, September 16: 12 a.m  to 4:30 a.m.
  • Tuesday, September 17: 12 a.m  to 4:30 a.m.
  • Wednesday, September 18: 12 a.m  to 4:30 a.m.
  • Thursday, September 19: 12 a.m  to 4:30 a.m.
  • Friday, September 20: 12 a.m. to 4:30 a.m.
  • Saturday, September 21: 12 a.m. to 4:30 a.m.

Roadwork on the King Street to I-395 NB on ramp will require overnight total ramp closures. A detour will be in place. Weather permitting the closure will take place during the following times:

  • Monday, September 16: 12 a.m  to 4:30 a.m.
  • Tuesday, September 17: 12 a.m  to 4:30 a.m.
  • Wednesday, September 18: 12 a.m  to 4:30 a.m.
  • Thursday, September 19: 12 a.m  to 4:30 a.m.
  • Friday, September 20: 12 a.m. to 4:30 a.m.
  • Saturday, September 21: 12 a.m. to 4:30 a.m.

Roadwork along I-395 south will require overnight total closures of the I-395 SB exit ramp on to Duke Street (Exit 3A). A detour will be in place. Weather permitting the closure will take place during the following times:

  • Monday, September 16: 12 a.m  to 4:30 a.m.
  • Tuesday, September 17: 12 a.m  to 4:30 a.m.
  • Wednesday, September 18: 12 a.m  to 4:30 a.m.
  • Thursday, September 19: 12 a.m  to 4:30 a.m.
  • Friday, September 20: 12 a.m. to 4:30 a.m.
  • Saturday, September 21: 12 a.m. to 4:30 a.m.

Roadwork along I-395 south will require overnight total closures of the I-395 SB exit ramp on to westbound Edsall Road (Exit 2B). A detour will be in place. Weather permitting the closure will take place during the following times:

  • Monday, September 16: 12 a.m  to 4:30 a.m.
  • Tuesday, September 17: 12 a.m  to 4:30 a.m.
  • Wednesday, September 18: 12 a.m  to 4:30 a.m.
  • Thursday, September 19: 12 a.m  to 4:30 a.m.
  • Friday, September 20: 12 a.m. to 4:30 a.m.
  • Saturday, September 21: 12 a.m. to 4:30 a.m.

Roadwork along I-395 will require overnight closures of the Shirlington Circle to I-395 north ramp. A detour will be in place. Weather permitting the closure will take place during the following times:

  • Monday, September 16: 12 a.m  to 4:30 a.m.
  • Tuesday, September 17: 12 a.m  to 4:30 a.m.
  • Wednesday, September 18: 12 a.m  to 4:30 a.m.
  • Thursday, September 19: 12 a.m  to 4:30 a.m.
  • Friday, September 20: 12 a.m  to 4:30 a.m.
  • Saturday, September 21: 12 a.m  to 4:30 a.m.

Roadwork along I-395 will require overnight closures of the South Glebe Road to I-395 north ramp. A detour will be in place. Weather permitting the closure will take place during the following times:

  • Monday, September 16: 12 a.m  to 4:30 a.m.
  • Tuesday, September 17: 12 a.m  to 4:30 a.m.
  • Wednesday, September 18: 12 a.m  to 4:30 a.m.
  • Thursday, September 19: 12 a.m  to 4:30 a.m.
  • Friday, September 20: 12 a.m. to 4:30 a.m.
  • Saturday, September 21: 12 a.m. to 4:30 a.m.

Roadwork along I-395 will require overnight closures of the eastbound Duke Street to I-395 south ramp. A detour will be in place. Weather permitting the closure will take place during the following times:

  • Monday, September 16: 12 a.m  to 4:30 a.m.
  • Tuesday, September 17: 12 a.m  to 4:30 a.m.
  • Wednesday, September 18: 12 a.m  to 4:30 a.m.
  • Thursday, September 19: 12 a.m  to 4:30 a.m.
  • Friday, September 20: 12 a.m. to 4:30 a.m.
  • Saturday, September 21: 12 a.m. to 4:30 a.m.

Roadwork along I-395 north will require overnight total closures of the I-395 NB exit ramps on to Route 27/Washington Blvd (Exit 8A) and Route 27 North/110 South (Exit 8B). A detour will be in place. Weather permitting the closure will take place during the following times:

  • Monday, September 16: 12 a.m  to 4:30 a.m.
  • Tuesday, September 17: 12 a.m  to 4:30 a.m.
  • Wednesday, September 18: 12 a.m  to 4:30 a.m.
  • Thursday, September 19: 12 a.m  to 4:30 a.m.
  • Friday, September 20: 12 a.m. to 4:30 a.m.
  • Saturday, September 21: 12 a.m. to 4:30 a.m.

Roadwork along I-395 north will require an overnight, single-lane closure on the right regular lanes between Glebe Road and Washington Boulevard. Weather permitting, closures may take place on the following nights:

  • Monday, September 16: 12 a.m  to 4:30 a.m.
  • Tuesday, September 17: 12 a.m  to 4:30 a.m.
  • Wednesday, September 18: 12 a.m  to 4:30 a.m.
  • Thursday, September 19: 12 a.m  to 4:30 a.m.
  • Friday, September 20: 12 a.m  to 4:30 a.m.
  • Saturday, September 21: 12 a.m  to 4:30 a.m.

Due to scheduled work for the I-395 Express Lanes project, ramps will be narrowed at Duke Street and Seminary Road during the following times:

  • Monday, September 16: 10 a.m  to 3 p.m. if northbound; 9 a.m. to 2:30 p.m. if southbound
  • Tuesday, September 17: 10 a.m  to 3 p.m. if northbound; 9 a.m. to 2:30 p.m. if southbound
  • Wednesday, September 18: 10 a.m  to 3 p.m. if northbound; 9 a.m. to 2:30 p.m. if southbound
  • Thursday, September 19: 10 a.m  to 3 p.m. if northbound; 9 a.m. to 2:30 p.m. if southbound

Due to scheduled work for the I-395 Express Lanes project, the Quaker Lane approach to Shirlington Circle has been narrowed to accommodate work in this area. During overnight hours, the Quaker Lane approach to Shirlington Circle will be closed, with a detour is in place. Weather permitting, this closure will occur during the following times:

  • Monday, September 16: 10 p.m. to 5 a.m.
  • Tuesday, September 17: 10 p.m. to 5 a.m.
  • Wednesday, September 18: 10 p.m. to 5 a.m.
  • Thursday, September 19: 10 p.m. to 5 a.m.
  • Friday, September 20: 10 p.m. to 6 a.m.
  • Saturday, September 21: 10 p.m. to 6 a.m.
  • Sunday, September 22: 10 p.m. to 5 a.m.

Due to scheduled bridge rehabilitation work on I-395 South, multi-lane closures are expected approaching the areas of Sanger Avenue and Braddock Road. Weather permitting, closures and HOV restrictions will be in place throughout the weekend starting the evening of Friday, September 20, through the morning of Monday, September 23.

Where to go

When it comes to closures, it’s important to drive safely. If you’re travelling through the area during these times, just look out for the on-road signage and stay alert. You can also sign up for e-newsletters and traffic alerts on the Contact Us page.

Safe Travels,
The Express Lanes Team